Responsibility in PRINCE2 Customer/Supplier Environment: Supplier's Role

Supplier's Role

Question

Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

B.

In a PRINCE2 customer/supplier environment, there are two main roles: the customer who commissions the project and the supplier who delivers the project. The customer is responsible for defining the requirements and accepting the final product, while the supplier is responsible for delivering the product to meet the customer's requirements.

Of the options listed, option B, "Provide the resources and skills to deliver the desired result," is the responsibility of the supplier. This means that the supplier is responsible for providing the necessary resources, such as personnel, equipment, and materials, and the skills required to deliver the project to the customer's requirements.

Option A, "Specify the desired result," is the responsibility of the customer. The customer should define what they want to achieve with the project and communicate this clearly to the supplier. The supplier will then use this information to deliver the project to meet the customer's requirements.

Option C, "Pay for the project," is not a responsibility of either the customer or the supplier, but rather a contractual agreement between the two parties. The customer pays the supplier for the work performed, and the supplier delivers the project to meet the customer's requirements.

Option D, "Specify the benefits of the project," is also the responsibility of the customer. The customer should define the benefits they expect to achieve from the project, such as increased revenue or improved efficiency. The supplier will then use this information to deliver the project to meet the customer's desired benefits.

In summary, in a PRINCE2 customer/supplier environment, the supplier's responsibility is to provide the resources and skills required to deliver the project to meet the customer's requirements. The customer is responsible for defining the requirements, specifying the desired result and benefits, and paying for the project.