Identify the missing word in the following sentence: A purpose of the [?] theme is to control any unacceptable deviations from the project's objectives.
Click on the arrows to vote for the correct answer
A. B. C. D.C.
The missing word in the sentence is "Change".
The sentence suggests that the theme is related to controlling any deviations from the project objectives. The word "change" is commonly associated with modifications, adjustments or alterations in plans, processes, or deliverables. In the context of project management, change management refers to a structured approach to managing any changes in project scope, schedule, or budget.
Controlling any unacceptable deviations from project objectives requires a project manager to identify the root cause of such deviations and take corrective actions. Change management is an essential component of project management that enables project managers to manage deviations from project objectives and ensure that the project stays on track.
Option A "Change" is the correct answer to this question. Option B "Plans" are specific to project objectives and may not necessarily control deviations. Option C "Progress" does not directly relate to controlling deviations from objectives. Option D "Risk" is more associated with identifying and mitigating potential risks that may cause deviations from project objectives.