Re-Registration Exam: Objective of Directing a Project Process

Objective of Directing a Project Process

Question

Which is an objective of the Directing a Project process?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

B.

The objective of the Directing a Project process in PRINCE2 is to provide overall direction and management to the project, ensuring that it remains aligned with the organization's objectives and strategies. The process involves setting up the project board, which is responsible for overseeing the project and making key decisions.

Out of the options given, option B - Ensure corporate or programme management has an interface to the project - is the most accurate objective of the Directing a Project process.

Option A - Review and approve a project mandate - is a part of the Starting up a Project process, which aims to ensure that there is a clear understanding of the project's objectives and scope before the project is initiated.

Option C - Define how risks, issues, and changes will be managed - is a part of the Managing a Stage Boundary process, which is responsible for reviewing the progress of the project and deciding whether to continue with the current stage or to initiate a new stage.

Option D - Obtain approval for completed products - is a part of the Controlling a Stage process, which is responsible for managing the day-to-day activities of the project and ensuring that products are delivered on time, within budget, and to the required quality standards.

Therefore, the correct answer to the question is B - Ensure corporate or programme management has an interface to the project.