Question 124 of 200 from exam PRINCE2-PRACTITIONER: Practitioner Project Management Certification

Question 124 of 200 from exam PRINCE2-PRACTITIONER: Practitioner Project Management Certification

Question

Scenario - Additional Information - Extract from the Communication Management Strategy.

The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.

Introduction

1. This document contains details of how the project
management

team will send information to individuals working on the
Calendar project, and receive information from them

Communication
procedure

72. See MNO Manufacturing Company standards for all
intemal company communications.

Tools and techniques

3. Use the staff newsletter to launch thelabel design
competition and to promote the chosen label design.

4. Using the number of responses to the label design
competition as a measure, report fortnightly to the Project
Board on the effectiveness of the staff newsletter as a
vehicle for communication.

5. Use the company website to advertise the promotional
calendar to customers

‘Records

6.A record should be maintained for each product of the
project. As a minimum this should show the project name,
product name, product title, and version number.

7. Extemal email and correspondence relating to the
Calendar project should be recorded electronically in the
project folder.

8. Information received in hard copy should, where
possible, should be scanned and filed as above,

Timing of
communication
activities

9. At the end of each stage, audit and report on the
performance of the communication methods being used
10. Highlight Reports to be provided to appropriate
stakeholders, at the frequency defined in each Stage Plan.

Stakeholder analysis:
Interested parties

11. Photographer.
12. Print company.

Tnformation needs for
each interested party

13. Weekly updates will be provided by email to the
individual producing the staff newsletter.

14. Engineering Manager is to be consulted when preparing
the photo session schedule.

Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.

The project is now at the end of the initiation stage.

Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process.

No Project Brief has been produced.

Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PID)

The PID includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description.

Short sections are also included for each of the strategies and the controls to be applied.

The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality - results.

After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized.

While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.

This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information.

Which statement applies to the Information needs for each interested party section?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C.

C.