PRINCE2 Foundation: Project Board Responsibility for Assurance

Project Board Responsibility for Assurance

Question

Identify the missing word in the following sentence.

A member of the Project Board is responsible for [ ? ] assurance.

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

B.

The missing word in the sentence is "quality."

In project management, the Project Board is the key decision-making body responsible for providing direction and ensuring that the project meets its objectives. One of the Project Board's responsibilities is to oversee the quality assurance of the project's deliverables.

Quality assurance is the process of verifying that the project's products or deliverables meet the established quality standards. It involves a systematic approach to identifying and addressing any issues or defects in the deliverables before they are delivered to the customer.

Therefore, it is crucial for a member of the Project Board to have knowledge and expertise in quality assurance to ensure that the project's deliverables meet the desired quality standards.