Question

A vendor has accepted a proposed project from a customer.

Which of the following is MOST likely to be the first document created by the project manager?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

C.

299

The correct answer is A. Project charter.

A project charter is a document that formally authorizes a project, defines the project scope, objectives, and stakeholders, and provides a high-level overview of the project. It is the first document that should be created by the project manager because it sets the foundation for the project and provides a framework for all other project activities.

The project charter typically includes the following elements:

  1. Project description: This section provides a brief overview of the project, including its purpose, goals, and objectives.

  2. Project scope: This section defines the boundaries of the project, including what is included and what is excluded.

  3. Project objectives: This section outlines the specific goals and objectives of the project.

  4. Project stakeholders: This section identifies the key stakeholders involved in the project, including the customer, project team, and other relevant parties.

  5. Project assumptions and constraints: This section lists the assumptions and constraints that are relevant to the project, such as budget limitations, timeline restrictions, and resource availability.

  6. Project risks: This section identifies potential risks that could impact the project, along with strategies for mitigating those risks.

  7. Project milestones: This section outlines the major project milestones, including the expected completion date for each milestone.

By creating a project charter, the project manager ensures that all stakeholders have a shared understanding of the project, its objectives, and its scope. This helps to minimize misunderstandings and ensures that everyone is working towards the same goals. Additionally, the project charter provides a reference point for all project decisions, helping to keep the project on track and within scope.