CompTIA Project+: Project Phases and WBS Creation

Project Phases

Question

A project manager is creating the WBS.

In which of the following phases is the project?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

B.

139

The Work Breakdown Structure (WBS) is a hierarchical decomposition of the project deliverables into smaller, more manageable components. It is typically created during the planning phase of the project and serves as a basis for organizing and controlling the project's scope, schedule, and budget.

Therefore, based on the information provided in the question, the project manager is creating the WBS, indicating that the project is currently in the planning phase.

Option B - Planning is the correct answer. The other options are as follows:

A. Initiation: This phase involves the initial planning, defining the project objectives, identifying stakeholders, and obtaining approval to start the project. It is the first phase of the project life cycle and precedes the planning phase.

B. Execution: This phase involves the actual execution of the project plan, where the project team carries out the tasks defined in the WBS. It is the third phase of the project life cycle and follows the planning phase.

C. Closing: This phase involves the formal closure of the project, where the project is reviewed, and the final deliverables are accepted by the stakeholders. It is the last phase of the project life cycle and follows the execution phase.

In summary, the project is in the planning phase, and the correct answer is B. Planning.