Which of the following statements about the Closing a Project process are true? 1.The Closing a Project process provides a fixed point for the receipt of completed Work 2.The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.
Packages for the work performed in the final stage.
Click on the arrows to vote for the correct answer
A. B. C. D.B.
The Closing a Project process is the final process in the PRINCE2 project management methodology. It is the process that ensures that a project has been completed in a controlled and organized way, and that the project's objectives have been achieved. It also provides a formal and fixed point to review the project and its outcomes.
Now, let's review each statement and determine if it is true or false:
This statement is true. The Closing a Project process provides a fixed point for the receipt of completed work packages. Work packages are a key element of PRINCE2, and they are used to break down a project into manageable chunks of work that can be completed by a single team or individual. The Closing a Project process provides a formal acceptance of the completed work packages, which ensures that all the work has been completed to the required standard and that the project team can move on to the next stage of the project life cycle.
This statement is also true. The Closing a Project process provides a formal and fixed point to review the project's objectives and outcomes. During this process, the project team reviews the original Project Initiation Documentation (PID) and compares it with the actual results achieved during the project. This review helps to identify any deviations from the original plan and to learn from them for future projects.
Therefore, both statements are true, and the correct answer is option C: "Both 1 and 2 are true."