Which of the following statements is NOT true regarding the risk management plan?
Click on the arrows to vote for the correct answer
A. B. C. D.C.
The risk management plan details how risk management processes will be implemented, monitored, and controlled throughout the life of the project.
The risk management plan does not include responses to risks or triggers.
Responses to risks are documented in the risk register as part of the Plan Risk Responses process.
Incorrect Answers: A, B, D: These all statements are true for risk management plan.
The risk management plan details how risk management processes will be implemented, monitored, and controlled throughout the life of the project.
It includes thresholds, scoring and interpretation methods, responsible parties, and budgets.
It also acts as input to all the remaining risk-planning processes.
The correct answer is B: The risk management plan is an input to all the remaining risk-planning processes.
Explanation:
The risk management plan is a crucial document that describes how the organization will approach and execute the risk management process. The plan typically contains several components that aid in the effective management of risk. Let us discuss each of the given statements in detail to identify which one is not true:
A. The risk management plan is an output of the Plan Risk Management process: This statement is true. The Plan Risk Management process is the first process in the Risk Management Knowledge Area, which involves defining how the organization will conduct risk management activities throughout the project or program. The output of this process is the risk management plan.
B. The risk management plan is an input to all the remaining risk-planning processes: This statement is not true. While the risk management plan is an essential input for many processes in the Risk Management Knowledge Area, it is not an input to all remaining risk-planning processes. For instance, the Identify Risks process does not require the risk management plan as an input.
C. The risk management plan includes a description of the risk responses and triggers: This statement is true. Risk responses and triggers describe how the organization will respond to risk events and what will trigger the response. These responses may include mitigating the risk, accepting the risk, transferring the risk, or avoiding the risk.
D. The risk management plan includes thresholds, scoring and interpretation methods, responsible parties, and budgets: This statement is true. The risk management plan includes several components such as thresholds (the level of risk that is acceptable), scoring and interpretation methods (how to evaluate the probability and impact of identified risks), responsible parties (who is accountable for executing risk management activities), and budgets (the cost of risk management activities).
In summary, the correct answer is B, which states that the risk management plan is not an input to all remaining risk-planning processes. It is essential to understand the components of the risk management plan to effectively manage risks and ensure the success of the project or program.