Which is a purpose of the Managing Product Delivery process?
Click on the arrows to vote for the correct answer
A. B. C. D.B.
The purpose of the Managing Product Delivery process is to enable the Team Manager(s) to deliver the products defined within an agreed Work Package(s) to an acceptable level of quality, within the time and cost constraints agreed with the Project Manager. This process provides a controlled link between the Project Manager and the Team Manager(s), ensuring that the products are delivered according to the agreed requirements and that any issues or changes are managed appropriately.
Option A, "Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package," is not the purpose of the Managing Product Delivery process. While the Senior Supplier may be provided with information regarding the progress of the current Work Package, this is not the primary purpose of the Managing Product Delivery process.
Option C, "Enable the Project Board to request updates to the current Team Plan," is also not the purpose of the Managing Product Delivery process. The purpose of this process is to enable the Team Manager(s) to deliver the products defined within the Work Package(s) to an acceptable level of quality, within the time and cost constraints agreed with the Project Manager.
Option D, "Establish solid foundations for the project," is not the purpose of the Managing Product Delivery process. While the successful delivery of products within the Work Package(s) is important for establishing solid foundations for the project, this is not the primary purpose of this process.
In summary, the correct answer is B, "Provide a controlled link between the Project Manager and the Team Manager(s)." The Managing Product Delivery process is an important part of the PRINCE2 project management methodology, and it plays a critical role in ensuring that the products are delivered to an acceptable level of quality, within the time and cost constraints agreed with the Project Manager.