Techniques for Modifying Schedules based on Resource Constraints

Resource-Constrained Schedule Modification Techniques

Question

Which of the following techniques modifies the schedule based upon resource constraints?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

A.

The correct answer to the question is A. Critical Chain Method.

The Critical Chain Method (CCM) is a project management technique that modifies the schedule based upon resource constraints. CCM takes into account the availability of resources and the dependencies between project activities, and adjusts the schedule accordingly.

In CCM, project managers determine the critical path, which is the sequence of activities that must be completed on time for the project to finish on schedule. However, CCM also considers the availability of resources and identifies the critical chain, which is the longest sequence of activities that are resource-constrained. The critical chain typically includes activities that require the most time or resources, and may be affected by factors such as personnel availability, equipment, and supplies.

To manage the critical chain, CCM may use techniques such as resource leveling, which involves adjusting the schedule to ensure that resources are allocated efficiently. This may involve delaying non-critical activities or increasing the resources available for critical activities. CCM may also use buffer management, which involves adding additional time buffers to protect the critical chain from unforeseen delays or resource constraints.

In contrast, the other techniques listed in the question do not specifically modify the schedule based upon resource constraints. The Critical Path Method (B) is a project management technique that identifies the critical path, but does not take into account resource availability. The Arrow Diagramming Method (C) and Precedence Diagramming Method (D) are both project management techniques that use diagrams to illustrate the sequence and dependencies of project activities, but do not specifically address resource constraints.

In summary, the correct answer to the question is A. Critical Chain Method, which is a project management technique that modifies the schedule based upon resource constraints.