Prince2 Foundation Project Management Certification Exam - Minimum Requirement for Applying the Quality Theme

Minimum Requirement for Applying the Quality Theme

Question

Which is a minimum requirement for applying the quality theme?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

B.

http://prince2.wiki/Quality

In PRINCE2, the Quality theme is one of the seven themes that describe the essential aspects of project management. The Quality theme focuses on defining and implementing quality control and assurance measures throughout the project lifecycle to ensure that the project's products and deliverables meet the stakeholders' expectations.

To apply the Quality theme in a PRINCE2 project, there are some minimum requirements that need to be met. These requirements are:

B. To use the prescribed approach to quality management: PRINCE2 provides a structured approach to quality management, which includes defining the quality criteria, setting quality objectives, identifying the quality methods and techniques to be used, and assigning quality responsibilities to the project team members. The project manager must follow the PRINCE2 approach to quality management to ensure that the project's products and deliverables meet the defined quality criteria and objectives.

A. To use lessons to inform quality planning: The project team should review and learn from the quality-related lessons learned from previous projects or other sources, such as industry standards, regulations, or best practices. The lessons learned should be used to inform the project's quality planning, such as identifying potential quality risks, setting quality criteria, and determining the quality methods and techniques to be used.

C. To use external quality standards for quality control: External quality standards, such as ISO, industry-specific regulations, or customer requirements, may apply to the project's products and deliverables. The project team should identify these external quality standards and use them to define the project's quality criteria, objectives, and methods. The project team should also ensure that the project's products and deliverables meet these external quality standards.

D. To use user stories to inform the project product description: User stories are a technique used in agile project management to define the end-users' requirements and expectations. User stories can be used to inform the project's product description, which includes the quality criteria and objectives. By using user stories, the project team can ensure that the project's products and deliverables meet the end-users' expectations and requirements.

Therefore, the minimum requirement for applying the Quality theme is to use the prescribed approach to quality management, which includes defining the quality criteria, setting quality objectives, identifying the quality methods and techniques to be used, and assigning quality responsibilities to the project team members.