When should the level of tailoring be defined?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

C.

https://www.prince2primer.com/tailoring-prince2-methodology/

The level of tailoring refers to the degree to which the project management methodology, processes, and procedures should be customized or modified to suit the specific requirements of a given project. The level of tailoring affects the overall project approach, including project planning, risk management, communication, monitoring and control, and project closure.

To answer the question, the most appropriate time to define the level of tailoring is before the project is triggered by the project mandate. The project mandate provides the initial information about the project, including the high-level objectives, scope, and constraints. It is essential to determine the level of tailoring early in the project life cycle to ensure that the appropriate project management approach is established from the outset.

Defining the level of tailoring at the initiation stage enables the project manager to identify the appropriate project management methodology and processes that are suitable for the project. The project manager can then tailor these methodologies and processes to fit the specific requirements of the project, ensuring that the project is delivered successfully.

Although reviewing what has been learned to date may provide valuable insights into the level of tailoring required, it is not the most appropriate time to define it. The risks and issues experienced during the project may also influence the level of tailoring required. However, waiting until issues and risks arise to define the level of tailoring can lead to delays in project delivery and additional costs.

Therefore, the best approach is to define the level of tailoring before the project is triggered by the project mandate. This will enable the project manager to establish the appropriate project management approach and ensure that the project is delivered successfully within the specified constraints.