Continued Business Justification: False Statements Revealed | Prince2 Practitioner Exam

False Statements Regarding Continued Business Justification

Question

Which of the following statements is FALSE regarding the Continued Business Justification?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

B.

The correct answer to this question is A. "The justification for the project must remain the same throughout the project" is false regarding Continued Business Justification.

Continued Business Justification is one of the seven principles of PRINCE2, a project management framework widely used in many industries. It requires that the project remains justified from the start of the project until its completion.

The project justification is typically based on a business case, which outlines the reasons for the project and the expected benefits, costs, and risks. The business case is developed during the initiation stage of the project and is regularly reviewed and updated throughout the project's life cycle.

However, it is possible for the justification for the project to change during the project's life cycle. For example, new information may come to light that changes the expected benefits or costs, or external factors may change that affect the project's justification. In such cases, it may be necessary to update the business case and review the justification for the project.

Therefore, statement A, which states that the justification for the project must remain the same throughout the project, is false. The justification for the project should remain valid, but it may change if there are valid reasons to do so. If it is determined that the project is no longer justified, then statement D, which states that the project should be stopped, is true.