Exception Plan Triggers | Prince2 Practitioner Exam - Project Management Certification

Activities Triggering Exception Plan

Question

Which of the following activities could trigger the production of an exception plan?

Answers

Explanations

Click on the arrows to vote for the correct answer

A. B. C. D.

B.

An exception plan is a contingency plan that outlines the steps that will be taken to manage a project when it deviates significantly from its original plan. It is designed to provide a clear path forward when unexpected events occur and can help to ensure that the project stays on track and is delivered successfully.

Out of the four activities listed, three could trigger the production of an exception plan. Let's take a closer look at each one:

A. Review Stage status: During project execution, it is common to conduct regular status reviews to assess progress against the project plan. If the review reveals that the project is not on track, or that key deliverables are at risk, this could trigger the production of an exception plan. The plan would outline the steps that will be taken to bring the project back on track and ensure that the necessary deliverables are completed within the required timeframe.

B. Giving ad hoc direction: Ad hoc direction refers to unplanned changes to the project plan that are not part of the original scope or requirements. These changes could arise due to shifting priorities, changes in stakeholder needs, or unforeseen events. If ad hoc direction is given, and it is likely to have a significant impact on the project's timeline, budget, or scope, then an exception plan may need to be produced. The plan would outline the steps that will be taken to manage the change and ensure that the project remains on track.

C. Escalating a project issue: When a project issue is escalated, it means that it has been raised to a higher level of management or authority for resolution. This could occur when an issue cannot be resolved at the project level, or when it requires additional resources or support to be resolved. If the issue is significant enough to cause a deviation from the project plan, then an exception plan may need to be produced. The plan would outline the steps that will be taken to manage the issue and ensure that the project remains on track.

D. Report stage end: The report stage is typically the final stage of a project, during which a final report is produced that summarizes the project's achievements, outcomes, and lessons learned. If, at the end of the report stage, it becomes clear that the project has not met its objectives, or that there are significant deviations from the original plan, then an exception plan may need to be produced. The plan would outline the steps that will be taken to manage the project's outcomes and ensure that any outstanding issues are resolved.

In summary, three of the four activities listed could trigger the production of an exception plan: Review Stage status, Giving ad hoc direction, and Escalating a project issue. Report stage end, while important for assessing project outcomes, is less likely to trigger the production of an exception plan, as the project is typically complete at this point.