Identify the missing words in the following sentence.
An objective of the Closing a Project process is to ensure that provision has been made to address [?] through follow-on action recommendations.
Click on the arrows to vote for the correct answer
A. B. C. D.C.
The objective of the Closing a Project process is to ensure that all aspects of the project have been properly addressed and that the project can be formally closed. This involves ensuring that all project products have been delivered, all stakeholders have been satisfied, and that all project documentation has been completed.
One important aspect of the Closing a Project process is to ensure that provision has been made to address any open issues and risks that have been identified during the project. This is the key to the correct answer, which is C.
Option A (the measurement of benefits not yet realized) is not directly related to the Closing a Project process. It may be important in other project management processes, such as Benefits Management, but it is not a specific objective of the Closing a Project process.
Option B (the handover of products) is important in the Closing a Project process, but it is not the main objective of the process. Handover of products is covered in the Handover process.
Option D (the release of resources) is also important in the Closing a Project process, but it is not the main objective of the process. The release of resources is covered in the Resource Management process.
Therefore, the correct answer is C (open issues and risks), which is an important objective of the Closing a Project process.