During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?
Click on the arrows to vote for the correct answer
A. B. C. D.D.
During the Managing a Stage Boundary process in PRINCE2 methodology, the project manager reviews the progress of the current stage and decides whether to proceed with the next stage or to stop the project. The process involves updating various project documents to ensure that the project is on track and that the next stage can be started with confidence.
One of the key products that is updated during the Managing a Stage Boundary process is the Project Plan. The Project Plan is a comprehensive document that outlines the overall strategy for the project, including the scope, timelines, resources, and budget.
During the Managing a Stage Boundary process, the project manager updates the Project Plan with estimated costs and time for the stage that is about to begin. This includes updating the timelines and budgets for the next stage, as well as any changes to the overall project scope or objectives.
It's important to note that the Team Plan and Work Packages may also be updated during the Managing a Stage Boundary process, but these documents focus more on the specific tasks and responsibilities of the project team, rather than the overall project strategy and timeline. The End Stage Report is not updated during the Managing a Stage Boundary process, but is produced at the end of each stage to provide a summary of the stage's achievements, issues, and lessons learned.
In summary, the correct answer to the question is D. Project Plan.