Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete?
Click on the arrows to vote for the correct answer
A. B. C. D.B.
The project management team includes various roles responsible for different aspects of the project. In the context of PRINCE2 (Projects IN Controlled Environments), a widely used project management methodology, the role that represents the interests of those who will operate the project's products to realize the benefits after the project is complete is the Senior User.
The Senior User is responsible for representing the user community and ensuring that the project's products meet their needs and expectations. They are the primary stakeholders for the project's products and have the authority to specify and prioritize requirements for them. They also provide input on how the products will be used and what benefits they will provide.
The Senior User collaborates closely with the Project Manager and the Senior Supplier to ensure that the project's products are delivered on time, within budget, and to the desired quality. The Senior User also works with the Project Board to ensure that the project's objectives align with the organization's overall strategy and that the benefits are realized after the project is complete.
In summary, the Senior User is the project management team member responsible for representing the interests of those who will operate the project's products to realize the benefits after the project is complete. They are the primary stakeholders for the project's products and collaborate closely with the Project Manager and Senior Supplier to ensure their needs are met.